State Grid Corporation of China (SGCC) targets 140 GW of new‑type energy‑storage additions within its service territory under the 15th Five‑Year Plan to support large‑scale deployment of new‑type energy storage. China Southern Power Grid (CSG) will also push forward scaled‑up roll‑out, aiming to hit 60 GW of new‑type energy‑storage installed capacity by 2030.

On August 25, the two major state‑owned grid operators — State Grid and China Southern Power Grid — simultaneously released key signals for new‑grid development under the 15th Five‑Year Plan. As an emerging pillar industry, new‑type energy storage ranks among their core work priorities for this planning cycle.
State Grid issued Measures by State Grid Corporation of China to Support National Carbon‑Peaking Goals for the 15th Five‑Year Period. It sets an annual average of around 200 GW of newly‑added new‑energy capacity across its service territory for the 15th Five‑Year Plan.
State Grid will improve forecasting and dispatch capabilities for clean‑energy resources, strengthen scheduling for new‑energy farms and energy‑storage assets, optimise dispatch sequences for coal‑fired power units, and ramp up start‑stop peak‑shaving operations to maximise power output from renewables. It will boost source‑load interaction, accelerate virtual‑power‑plant development and enhance demand‑response capacity for load‑side resources. New electricity consumption will increasingly be covered by incremental clean‑energy generation, with new‑energy power output accounting for over 30 % of total generation within its service territory by 2030.
To enable larger‑scale new‑type energy‑storage development, State Grid plans 140 GW of new‑type energy‑storage additions in its operating area for the 15th Five‑Year Plan. It will deepen joint R&D with power generators, equipment manufacturers and research institutes to make breakthroughs on key technologies including long‑distance green‑power transmission from desert‑region bases, offshore‑wind‑power collection & delivery, and proactive support enabled by accurate new‑energy forecasting. R&D and deployment of long‑duration energy storage will also be accelerated.
On the same day, China Southern Power Grid published its interpretation of the 15th Five‑Year Roadmap for New‑type Power‑system Development.
Under CSG’s blueprint, the southern region will see 230 GW of new‑energy additions during the 15th Five‑Year Plan, reaching 500 GW by 2030. CSG will build 31 zero‑carbon industrial parks, together with five integrated source‑grid‑load‑storage demonstration projects and four green‑power direct‑connection pilot schemes.
CSG will prioritise scaled‑up new‑type energy‑storage roll‑out, targeting 60 GW of installed new‑type energy‑storage capacity by 2030, alongside 29.43 GW of pumped‑hydro storage. These assets will smooth volatile new‑energy output and lift overall system flexibility.
Combined, the two grid giants plan more than 1 230 GW of new‑energy additions and 200 GW of new‑type energy‑storage additions across their territories for the 15th Five‑Year Plan.
One week earlier, on August 18, State Grid and China Southern Power Grid held talks and signed the Strategic Cooperation Framework Agreement on Accelerating New‑type Power‑system Construction under the 15th Five‑Year Plan.
Both sides agreed to deliver reliable power supply, push ahead with new‑type power‑system construction and major power projects, advance the nationwide unified power market, boost energy‑power‑sector innovation, and share experience to advance high‑quality energy‑power development.
In addition, the National Development and Reform Commission and National Energy Administration have released the 15th Five‑Year Plan for New‑type Power‑system Construction. It targets the preliminary completion of China’s new‑type power system by 2030, including:
‑ Non‑fossil‑fuel power generation to make up 50 % of total output;
‑ High‑quality integration of more than 2 800 GW of new‑energy capacity;
‑ National new‑type energy‑storage capacity to hit 300 GW;
‑ A charging‑infrastructure network capable of supporting over 110 million electric vehicles.
At its regular press briefing in May 2026, the NDRC noted that China’s new‑grid investment is projected to exceed RMB 5 trillion for the 15th Five‑Year period. Earlier this year, State Grid unveiled an investment plan totalling RMB 4 trillion, a 40 % increase versus the 14th Five‑Year cycle.
Joint strategic moves by the two major grid SOEs together with top‑level policy design are quietly accelerating profound transformations shaping China’s power landscape over the next five years.
Research institute EVTank forecasts that booming global new‑type energy‑storage installations plus surging datacenter‑storage demand will push global energy‑storage‑battery shipments above 900 GWh in 2026. Global energy‑storage‑battery demand will surpass 2 TWh by 2030.
Source: Battery Hundred‑People Association / Battery.com.cn
Author: Xiao He